Architectural drawing shows existing courthouse and five-story addition (top), existing jail and addition, and new parking lots. [COOPER-HASKELL]
If Henderson County commissioners greenlight a $215 million courthouse-jail expansion in the coming weeks, employees and visitors at the three-story existing courthouse would begin to see massive change starting in the first quarter of 2025.
New parking areas, construction fencing, heavy machinery and lots of dump trucks would become a daily part of a disrupted landscape on Grove Street between Second and Fourth avenues.
“Being that we're six square blocks downtown in a fully occupied facility, it was important that we made sure that we stay contained within our footprint,” John Albro, senior project director, told commissioners last Wednesday. “This is a very large project. It's very significant. We're going to be bringing in approximately 26,000 yards of dirt, moving 50,000 yards of dirt — all of this in an occupied, active urban setting.”
During the meeting, the construction management team made up of Hendersonville-based Cooper Construction Co. and Florida-based Haskell Co. presented commissioners a cost estimate of $215,032,100 for the courthouse-jail project, a figure that Albro acknowledged “might be little more robust than what might have been anticipated.”
County Commission Chair Rebecca McCall assigned commissioners Michael Edney and Bill Lapsley to work with the Cooper-Haskell engineers to identify cost cuts. Among the options are proceeding now on just one of the two renovation-expansion projects — the courthouse or jail — or finding other trims.
“In our preliminary analysis, we’ve identified some potential opportunities (to reduce the total price), and we'd be very eager to see how we could support that decision-making process by listening, hearing what your priorities are or understanding what kind of refinements or suggestions might be worth setting out,” Abro said. He floated two ideas. Of the seven courtrooms, “there might be some opportunities to shell those spaces out for future development.” An underground parking garage could be scrapped.
Cost of the courthouse renovation and five-story addition came in at $112 million. The detention center renovation-expansion would cost $51.2 million. Sitework was estimated to cost $118 million for a total construction cost of $175 million. Included in the number is design contingency of $17.5 million and cost escalation allowance of $10.6 million.
The “soft cost” of $40 million includes furniture and equipment $12.5 million, architects' fee ($11.9 million), construction-manager-at-risk fee and permitting fees.
Albro and Joe Tripi, Haskell’s vice president and market construction leader, presented details of the cost and timeline of the project. Here is how contractors would phase the renovation work and courthouse and jail additions over 34 months from early 2025 to October 2027:
Here are other highlights the project management team presented: